Fibre addition unit
ARTICLE
This quarry decided to use the loose fibre system for the fibre addition to the coating plant to make Stone Mastic Asphalt. The fitters devised a system which ties into the current plant controls. It eliminates the need for manual handling of fibre bags and repeated entry to the plant to add pellets. The 1 tonne bags have to be raised above the hopper before they can be untied. To ensure that no one is under a supported load, the site installed a bag support frame, which is a sturdy reinforced piece of equipment that ensures no-one risks being crushed by the bags.



ARTICLE IMAGES




pdf document available
Go back to search critera
Sharing health and safety resources helps us all work towards Zero Harm
  • Aggregates |

  • Asphalt |

  • Cement |

  • Contracting |

  • Dimension Stone |

  • Lime |

  • Precast Concrete |

  • Mortar |

  • Readymix |

  • Recycling |

  • Silica Sand |