Best Practice

LOCATION: Asphalt/Coating plant ARTICLE YEAR 2009
ACTIVITY: Access & Egress & Working at Height COMPANY: Aggregate Industries
SUB ACTIVITY: N/A COMPANY LOCATION: Rand Asphalt Plant, Merseyside
BEST PRACTICE No: BP638 COMPANY TEL: 01515 249740
COUNTRY OF ORIGIN: United Kingdom
TITLE  
A new way of sampling
ARTICLE
Site staff at the Rand Asphalt Plant were concerned about the way in which the sampling of filler was carried out from either the top of the silo or from the top of the tanker.

It was suggested that sampling could be carried out when loading tankers by the addition of a simple lockable chute to the inspection hatch of the screw conveyor.

A simple valve and chute were fabricated which have minimised the need for working at heights and the risk of dust being discharged into the air.
ARTICLE IMAGES
Click image to enlarge



pdf document available
Go back to search critera
Sharing health and safety resources helps us all work towards Zero Harm